Third Consultation and Payment
Finally agreed our kitchen layout and made the final payment. Once the contract is final, there is only one or two days grace to change anything before it is uploaded to  the factory. There are however 3 things that the purchaser should pay attention to before final payment, ie:
a) Section 2.10 of the Conditions of Sale states that the customer should chect that all products listed on the order are the correct model and specification. Now the Wren Contract list of items does not normally specify make and model of appliances for example......you should request clarification.
b) Section 7.1 states  that Wren will deliver the products ordered within 30 days of the Order Summary or by the delivery date agreed at the time of the Order.
c) There is a degree of misinformation floating about regarding the clearances required by surfaces adjacent to cooking appliances. Distances are defined in HSE Technical Bulletin 022, 2014. Wall cupboards must be at least 460mm above the hob and an extractor hood must be at least 760mm above the hob, If the extractor hood is 100mm wider than the hob then wall cupboards can be butted up against the hood.

No comments:

Post a Comment

Completion The kitchen has been completed now for a few weeks apart from a few minor snagging items to sort out. The final result is shown...